Things to do...

If you haven't seen or heard from us in awhile, here's a little walk through of what we've been doing for the past 4 months - building a house!  We had most of it sub-contracted out, but we did the electrical & painting ourselves. Needless to say, we've learned a lot about what to do & not-to-do!

We're down to the last 3 weeks, so it's getting crazier than ever around here. The goal is to be moved in 100% by the end of spring break. After that - the doors are open!

Things that still have to be done:

  • plumber install all sinks/faucets/toilets/appliances & get water running
  • a/c company finish installing a/c
  • propane company to install gas lines & convert dryer/stove to propane
  • finish priming & painting door frames
  • prime/paint all of the shelves & cabinet doors
  • wash & paint the outside trim
  • install all of the interior lights & fans
  • install all of the light switches
  • pick out, purchase, & hope you got the right stuff for all the hardware on the cabinets
  • install exterior lights (after we find something that we can agree on)
  • have floors polished
  • touch-up paint in all the rooms
  • CLEAN all the dust - we'll be moping from ceiling to floor to get all the dust
  • Clean windows & install screens
  • sleep between the hours of 1-3am & then drink lots of coffee or Dr Pepper
If you're interested in cleaning or painting, come on by. We'll definitely put you to work!